Difference between revisions of "Dry Island - Bamboo Hills"

From LinuxWorks Minetest Server Wiki
Jump to navigation Jump to search
Line 2: Line 2:
 
| map =
 
| map =
 
{{BS-map|inline=yes|map=
 
{{BS-map|inline=yes|map=
{{BSe|KBHFa||[[Bamboo Hills]]}}
+
{{BS|KBHFa||[[Bamboo Hills]]}}
 
{{BS|TUNNEL1||}}
 
{{BS|TUNNEL1||}}
 
{{BS|TUNNEL1||}}
 
{{BS|TUNNEL1||}}
{{BSe|HST||[[Laza's Field]]}}
+
{{BS|HST||[[Laza's Field]]}}
 
{{BS|BRÜCKE1}}
 
{{BS|BRÜCKE1}}
{{BSe|HST||[[No Idea]]}}
+
{{BS|HST||[[No Idea]]}}
 
{{BS|hKRZWae}}
 
{{BS|hKRZWae}}
 
{{BS|TUNNEL1||}}
 
{{BS|TUNNEL1||}}
Line 13: Line 13:
 
{{BS|BHF||[[Tanh Cliffs]]}}
 
{{BS|BHF||[[Tanh Cliffs]]}}
 
{{BS|ABZrf||[[Euler_Street-Wolf_Rock_Railway|to Trisiston]]}}
 
{{BS|ABZrf||[[Euler_Street-Wolf_Rock_Railway|to Trisiston]]}}
{{BS|eKBHFxe||[[Redwood]]}}
+
{{BS|KBHFxe||[[Redwood]]}}
 
{{BSe|xTUNNEL1||[[Luvr Tunnel]]}}
 
{{BSe|xTUNNEL1||[[Luvr Tunnel]]}}
 
{{BS|ENDExa}}
 
{{BS|ENDExa}}

Revision as of 10:49, 13 September 2019

Dry Island - Bamboo Hills
Route map
Bamboo Hills
Laza's Field
No Idea
to Spawn
Tanh Cliffs
to Trisiston
Redwood
Luvr Tunnel
Mom Junction (western station)
passing by northern station of Mom Junction
to Land's End
Dry Island

Dry Island - Bamboo Hills is a track leading from Dry Island to Bamboo Hills built by User:Hume2. It is 4.4km long. There are 5 tunnels and 3 bridges.

Stations

Criticism

The tunnel between Dry Island and Mom Junction is as straight as possible but it's called a slalom track.

During the construction, there was an incident with User:luvr because the track at Mom Junction was built above existing station building and the historical monumentality was ruined. Therefore, the bridge connecting the northern and western parts of Mom Junction was covered by leaves and hedges to make it more natural. User:luvr didn't want the track to lead through his neighbourhood and protected the area. Therefore the track from Mom Junction and Redwood was built in a retro style and Luvr Tunnel was built under luvr's area.

Operation

As of 2019-09-05, the line had no operations running on it. The northern section between Tanh Cliffs and Bamboo Hills was taken over by DURT, who would interlock the line and switch it over to Left-hand traffic. On September 5, 2019, the Server's railway administration decided to close the Luvr Tunnel and the tunnel from Mom Junction to Dry Island due to poor construction quality and 2-slopes. It will be decided in the future if these stretches will be rebuilt.

On 2019-09-09 the line from Bamboo Hills to Tanh Cliffs was brought up to standard and the first passenger service commissioned, with Och_Noe still to finish the viaduct before Bamboo Hills.